BCP - Butcher Creek Acclimation Pond
Status: DecommissionedGeneral Operational Period: Seasonally
Start Date: 4/21/2004 12:00 AM
End Date: 6/29/2019 12:00 AM
Butcher Creek Acclimation Pond, Wenatchee River Basin.
Contacts
Location
Operational History
Operational history describes the period the site was interrogating for PIT tags. The comments provide anecdotal information about the operation of the site during this period. Site operational periods are updated typically at the end of the calendar year.
Year | Start Date | End Date | Comments |
---|---|---|---|
2019 | 3/21/2019 12:00 AM | 6/29/2019 12:00 AM | Start and end dates based on file open and closed dates. |
2018 | No data received. | ||
2017 | 3/20/2017 12:00 AM | 7/8/2017 12:00 AM | Start and end dates based on file open and closed dates. |
2016 | No data received. | ||
2015 | 3/18/2015 12:00 AM | 6/27/2015 12:00 AM | |
2014 | Site was not operational during 2014 | ||
2013 | Site was not operational during 2013 | ||
2012 | 3/26/2012 12:00 AM | 6/21/2012 12:00 AM | Antenna A0 installed on March 26. Juvenile coho were transferred to the pond on March 27. Antenna B0 installed April 2. Volitional release ran from May 17 - June 21. |
2011 | 3/22/2011 1:30 PM | 6/30/2011 12:00 AM | One antenna at outflow of pond undtil April 23, when second antenna installed 20m downstream. |
2010 | 3/12/2010 12:00 AM | 6/8/2010 12:00 AM | Refer to the 2010 BCP event log for operational details. |
2009 | 3/9/2009 12:00 AM | 6/17/2009 12:00 AM | Fish were first ponded on March 10, 2009; the volitional release began on May 6. The last detection occurred on June 13; the detection system was removed on June 17, 2009. |
2008 | 3/22/2008 12:00 AM | 6/19/2008 12:00 AM | Monitoring began on March 22 and ceased on June 19. There was one system blackout at each antenna system due to high stream flows in Nasons Creek that required staff to move the detection system transceivers. BCPA1 was offline on 5/16 for 56 minutes between 21:00 and 21:56. BCPA2 was offline on 5/16 for 23 minutes between 21:36 and 21:59. Christa H. Strickwerda. July 21, 2008. |
2007 | There were no monitored releases at Butcher Creek Pond in 2007. | ||
2006 | There were no monitored releases at Butcher Creek Pond in 2006. | ||
2005 | 4/20/2005 12:00 AM | 7/20/2005 12:00 AM | Contact Keely Murdoch (keely@mid-columbia-coho.net), Cory Kamphaus (cory@mid-columbia-coho.net) or Christa Strickwerda (christa@mid-columbia-coho.net) for information regarding PIT tag detection activities at this acclimation pond. |
2004 | 4/21/2004 12:00 AM | 6/14/2004 12:00 AM | Contact Keely Murdoch (keely@mid-columbia-coho.net), Cory Kamphaus (cory@mid-columbia-coho.net) or Christa Strickwerda (christa@mid-columbia-coho.net) for information regarding PIT tag detection activities at this acclimation pond. |
Configuration
Configuration metadata includes details about the equipment used at the site to detect and record PIT tags. A new configuration sequence record is created when equipment is added or removed from the site and the period of time it was active. A configuration sequence without an End Date is currently active.
Antenna Group | Transceiver ID | Antenna ID |
---|---|---|
POND EXIT | 01 | 01 |
POND EXIT | 02 | 02 |
POND EXIT | 03 | 03 |
Site Configuration Diagrams:
Equipment History
Select a type to view the history of equipment installed at this site. A missing End Date implies the information about the equipment is current.
Equipment Code | Description | Start Date | End Date |
---|
No Photos
Event Log Summary
Event Date | Event Type | Comments |
---|---|---|
6/27/2015 12:00:00 AM | SiteDown | Site taken down on 6/27/2015. |
3/18/2015 11:23:00 AM | SiteUp | Site installed on 3/18/2015. |
12/31/2014 11:17:00 AM | General | BCP interrogation units were not used in 2014. |