EVENT LOG FOR SITE JUL The first line of each entry contains a date/time stamp & who is reporting. The most recent entry is listed first. Date Time Who ---------- ----- -------- 05/21/2013 06:43 Fortier After reconnecting power supply from 5/10 failure, antennas 2-6 came on and off line intermittently. Discovered on 5/13 that node canister 2 had electrical issues resulting in nodes 2-6 shutting down. Set up antennas 1- 3, however, 4 pm high winds lifted the antennas out of the water disconnecting all but antenna 1 from sequence. On 5/14 at 1250 reconfigured sequence to have 4 antennas fitted directly side by side to completely cover main thalweg. Most detections of juveniles occurring from 0600 - 1400. Operations normal ever since. Jason Fortier Senior Fisheries Technician PSMFC/IDFG 3316 16th St. Lewiston, ID 83501 208-799-5010 Jason.Fortier@idfg.idaho.gov 05/13/2013 08:02 Fortier Operations normal. Power supply failed last week resulting in a reduction of in voltage. Antennas 2-6 powered down around 1005 Friday May 10th. Lack of flows have left antennas 3-6 almost high and dry. Jason Fortier Senior Fisheries Technician PSMFC/IDFG 3316 16th St. Lewiston, ID 83501 208-799-5010 Jason.Fortier@idfg.idaho.gov 05/06/2013 06:14 Fortier Operations normal. Water substantially dropping. Currently ~220 cfs. Node 2 noise levels a little higher than normal. Voltage in has dropped from 24.7 - 23.6 since the beginning of operations. Jason Fortier Senior Fisheries Technician PSMFC/IDFG 3316 16th St. Lewiston, ID 83501 208-799-5010 Jason.Fortier@idfg.idaho.gov 05/01/2013 13:51 Fortier Around noon on 4/29, high winds disconnected antenna 3, 4, 5, and 6. One node canister was damaged. Site was pulled on 4/29 at 1200. Site reinstalled on 4/30 and turned on at 1700. 6 antennas fully operational. Flows dropping below 400 cfs. Jason Fortier Senior Fisheries Technician PSMFC/IDFG 3316 16th St. Lewiston, ID 83501 208-799-5010 Jason.Fortier@idfg.idaho.gov 04/29/2013 11:35 Fortier 2/26/2013 1042 - First time array was installed and operational. 3 antennas were set and operated until 3-1-2013 1320 when antenna 1 broke loose as flows increased. Site was pulled until flows dropped. No fish detections. 3/27/2013 1328 - Array reinstalled with 3 antennas. First detection occurred on 3/31/2013 0648. Site was pulled on 4/5/2013 1037 as a result of the master nodes plug being damaged. Temperature spikes on all 3 nodes resulted in a return to Biomark for electrical damage checks. Raft antennas were modified to handle higher velocities. 4/22/2013 1517 - 4 antennas were installed with new modifications. Multiple detections. System was shut down on 4/24/2013 1217 to install 2 more rafts. 4/24/2013 1453 - 2 more rafts were installed, a total of 6 in operation. Numerous detections with no problems. Jason Fortier Senior Fisheries Technician Idaho Department of Fish and Game 3316 16th St. Lewiston, ID 83501 208-799-5010 01/02/2013 00:00 PTOC_Bot Annual log file initiation for JUL #### End of Event Log for JUL ###